The extremely expert website staff at AJT Engineering has just lately accomplished the installation of a new 30″ Main Inlet Valve for a client’s small hydro power station.
เกจวัดแรงดันไอน้ำ , mixed with a Rotork SI-3 failsafe actuator, now supplies the shopper with full automation compared to the earlier handbook operation.
AJT designed, manufactured and installed a new spool piece in-house to match existing head to head dimensions. Whilst Cadherent provided designs for a assist for the Rotork actuators substantial failsafe spring mechanism – this too was then fabricated by AJT at our amenities in Aberdeen.
The installation was then finished off with new galvanised handrailing to protect from the pit opening.
Many thanks go to all our valued suppliers and contractors who continue to make these projects potential: Cadherent, Stoddard Crane Hire, VAG Group, Gareth Beck, Rotork, KGAL Consulting Engineers Ltd.